In May 1996, the ground breaking of a $184m renovation project took place. This project included construction of a new terminal, a parking garage, an air traffic control tower and a cargo facility. This project was financed with funds from airport improvement (AIP), the passenger facility charge (PFC) and airport revenue.
A new terminal of 16,000ft² was opened in 2000 along with the addition of two new jet bridges. The already existing terminal was demolished except for the expanded area. The runway 1/19 was extended from 400m to 2,600m during the renovation.